A refiner in Asia planned to clean 359 heat exchangers during a shutdown to regain process efficiencies and boost production.  The cleaning needed to be completed within a 21-day window.  During the shutdown, 40 more exchangers were found to need cleaning within the same 21-day schedule, making it 399 in total.